Tuesday, July 22, 2014

Asphalt work completed

Fontana Paving was out yesterday to patch a couple of small areas on the course. Next to 3 green and at the bottom of 4 near the red tee.  106 feet of asphalt was pulled up, rock placed down and 3" of asphalt laid. We have these areas roped off for a couple of extra days.  The areas are roped off to keep cart and equipment traffic away from these spots.  Remaining funds from the bunker project paid for this work. The area on 3 was damaged during construction of the bunkers.  We still must do some dirt work and grade changes around these two areas.

Asphalt removed and rock being laid in place near 3 green.

Asphalt  being finished up before rolling.

Finished

#4 Finished

No comments:

Post a Comment