Thursday, October 22, 2015

Driving Range Protective Net Nearly Completed

The staff has installed the wire border and put all the netting up on the Long Range Tee over the last 2 days. We have some additional work to do in the morning and hope to have the mats open by noon on Friday.
Netting rolled out and staff installing rope border.

Guys had to run the rope in and out of the netting so it can be attached to the wire.


Hanging netting on wire that was installed yesterday. 5/16" wire stretched across the top,down the poles and across the bottom where the net is attached to it using carbiner snaps that hold them in place.
Additional view of guys up on the lift. Skip and Russ doing this work.
Attaching more snaps in place. About every 3'.

The maintenance building side of the range that was finished for the most part on Wednesday.

No comments:

Post a Comment