Thursday, July 21, 2022

Day 2 Asphalt Overlay

 Had a pretty good day today but a couple issues cropped up. Laid overlay from 15 lake crossing through 13 tee and onto 12 but then it happened. 2” waterline gave way pouring a torrent of water down into the already wet area below the red tee on 12. We were able to get our 3 trucks asphalt out and laid, rerouted the trucks and moved over to 7 and pulled down to red tee on 7. Approximately 3,000 more feet with a little over 5,000 to go. Along with the work comes some additional damage due to the overall condition of the paths in some spots. 

We've been pretty much buried in work the past couple of days and have not had the opportunity to do much roping and staking in areas where the overlay does much up well with the soil around it. Please remember to use caution upon entering and exiting the new cart paths. We appreciate your understanding during this work. 


Blowout above 12 red tee. Luckily the shutoff was nearby and we were able to isolate  fairly quickly but not before hundreds of gallons ran down the hill.

Pulling out from the lake crossing at 15 tee.

Inevitably some damage going down the hill on 11. Brittle old asphalt ultimately won't hold up. Guys are pulling this out as I type and an extra layer of asphalt will be put in place.

Working toward 7 red tee.

Another area we were concerned about coming down hill in front of red tee on 12. Had about 20 trucks trips over this and it gave out. Luckily we routed trucks out a different way from the beginning of the day to reduce wear and tear which would have been much worse.