 Good progress on the cart path overlay today at Glen Echo.

The clubhouse circle was completed this morning and the operation was moved to the area of 3 tee and our contractor brought us to within about 200 yards from the first tee.

Thursday play will begin from the 10th tee to allow us some extra time to get through #1 tee. We will be asking members to go through the maintenance area to get to the driving range since we will be stacked with trucks along 1 and into the range area. Our road begins at the guard rail near the cart garage. We will then complete the long range road and parking area and then move out to #3. I anticipate 4 tee to the field bar road behind 7 green off of #4 completed on Friday.

The asphalt that is currently laid is ready to be driven upon. Once the asphalt is rolled a few times it will be ready to drive upon. In the meantime, if you are out on Thursday or Friday, we will provide some guidance in the area that we are working. I Thanks for your patience as we work through this project.

Areas ground on parking lot as contractor prepared to fill with new asphalt.

Rolling the newly patched area.

Laying asphalt in clubhouse circle.

Rolling the area smooth.
                                       Contractor using a paving machine to lay the asphalt. Staff firming up
                                        sides and smoothing out imperfections.


Steamy hot.
                   
Finished product after rolling from 2 tee to 1 green.

From 2 tee onward and up!

Asphalt on the high side of 1 will need some back bill and sod.


Area near the upside but on the low side with the same issue. Soil and sod to smooth out.
 This will prevent damage to equipment and reduce hazardous situations for carts and our members operating them. 