Monday, August 2, 2021

Cart Paths and Fairways

Over the next few days, there are a couple of large scale projects taking place on the grounds of Glen Echo CC.

Sunday evening we began to aerate our fairways. Skip and I came in once the last tee times went off and started pulling cores and then busting up the cores with a Flail mower that has spinning blades and chains and pulverizes the plugs. Today we will begin to drag the fairways with metal drags which breaks up any plugs that made it past the grinding. It will also help work the soil back through the zoysia canopy. We blow the remaining thatch and residue into the rough where it can be chewed up by the rough mower. Earth to earth and dust to dust. The fairways are then mowed. We anticipate this taking more than one day to complete all of our fairways. We normally have 3-4 fairways to complete usually on Tuesday and or Wednesday depending upon the weather conditions and anticipated play. 

Asphalt work will begin in earnest on Tuesday with the front clubhouse circle getting an overlay, Grinding along the edges of the crosswalks in the Pearson Plaza and near the portico will be completed and then a layer of asphalt will be laid in the circle area.We will begin asphalt on the course on Wednesday. The first work will be from the bottom of 3 hill all the way into the first tee and also the path that goes to the range.

Large dump trucks will be taken by our staff out into the field to assist in navigating through play. We will stage them in the parking lot and they will be brought out from there. They will also be brought back in once empty. Once the first section is complete, they will proceed to the second section which will be from the lowest point on hole 3 going forward through 4 tee to where it ties into the path behind 7 green. Those trucks will be staged  in the main entrance area, The new overlay will be 2" thick and we have a total linear footage of about 5,700' at an average width of about 8'.  

We anticipate this work to be completed by Friday. The asphalt will be able to be driven upon the next day. Depending upon weather, we will begin the process of back filling dirt in along the path and sodding fescue to help make a smooth transition with the new grade. We will do sections at a time to give us the best chance at growing the turf in properly since we are still into summer heat. I would not anticipate all the sodding to be completed before winter is upon us in December. Some areas might not need any back fill which will be helpful.

 

 

The sealing and striping of the parking lot is scheduled for Monday August 9th. Once the delays in the parking lot moved closer to our open window for the cart path overlay, the two projects were switched around so the sealing would not be damaged by the large asphalt trucks. This work should take 2-3 days next week.


We appreciate  your understanding during this time.Check you emails for updates and or social media for both the club and my personal accounts.

Instagram joewachter

Twitter jdwachter  Joe Wachter

Facebook  joewachter4


 




No comments:

Post a Comment