The staff keeps it rolling through the dramatic changes that are being made to the golf course. Day 28 brought the completion of Hole #3 as well as the near completion of #6, less some sodding. We embark on trenching #5 and #4 drainage installed, sanded and sodded hopefully before the rain comes Saturday night. The staff added sand to 4 bunkers on #3 and #6 and sodded around all of the bunkers except the front right on #6 which will be finished today.
|
#3 Bunkers Are COMPLETE!! |
We are currently at T-Minus 9 bunkers to go and the project will be complete!
|
The staff spreading sand in the front right bunker of #3. |
|
Sodding right bunkers of #3. |
|
Drain tile from the left bunker of #6 cut into the storm sewer galvanized pipe. |
|
Same from the two right bunkers of #6 cut into the storm sewer. |
|
Sodding of the right rear bunker of #6 right rear. |