 The staff have been busy this week on our storm drain repair in front of 6 green. Everything has been ripped out and new pipe has been connected between the start of the drain to the right of 6 approach connecting to the large surface drain to the left front of the approach.

Just a reminder, the 6th hole is closed to play as is the cart path. Please proceed back to the main road with carts and drive down to the 7th tee. We understand its a par 3 and many players could hit over the area to the green but we have a big mess in front of the green and did not want to take the chance someone could be injured walking around the area trying to retrieve a ball.

Gravel for the most part has been filled in around the pipe. Still have a bit more to add. Took about 50 tons. We will be capping the area with the soil that was removed, compact and then lay the sod back in place. We hope to have the hole back open for play sometime this coming week.

We will then begin to dig from 7 tee cart path across to the surface drain in 8 fairway. 

The course was a bit leafy this week with a large leaf drop over last weekend. We have 2-3 people cleaning greens, bunkers, blowing and mulching leaves daily while our most experienced staff is tackling the drainage project. We can usually do a pretty good job but a couple of high wind days early this week  made it difficult for us to catch up. Luckily, almost all trees have dropped their leaves except for the Pin Oaks which still have at least 50% of their leaves still holding on. They are beginning their drop but it will take a few more weeks.

Also, greens were cut twice this week from the aeration that occurred on November 2-4. Hopefully the rainfall this weekend will help settle the sand a bit more. Aeration holes have filled in nicely. Ready to throw some regulator on them before we put them to bed in the next few weeks to put a little shock into the poa annua. 

Skip digging out soil along the old 3' galvanized pipe.



First 20' of about 550 feet of pipe we are laying between 6 and 8 cart path.

Dropping in the gravel at the beginning of the project.


Tom digging out at the surface drain storm water chamber at the left front of 6 approach. Large surface drains were put in place about every 120' which helps get the surface water underground. Each chamber is large enough for you to step down into where the incoming and outgoing pipe are encased in concrete and brick. We made an sleeve that slips into the chamber out of the double walled pipe. We cut off about 3 of the ridges which reduces the size small enough for the pipe to slide into the existing holes. We then put some concrete patch around it to seal it completely.

Almost ready to connect the pipes. Didn't get the completed picture but coupled the pipes together and got a nice layer of rock on the pipe to keep it in place during the rain we are expecting over the weekend.