The staff worked early yesterday morning and finished #6. It looks great!
They also trenched and drained the left bunker on #5 and trenched the right bunker on #5.
We were planning to move to #4 today but potential rain is predicted for tonight and we want to get #5 completed. They have been torn out since around October 10th so it will be great to have this area complete.
The countdown will be down to T-7 by the end of today.
|
#6 IS COMPLETE |
|
Right side bunkers just completed. We plan on drilling and aerating some into the bermuda in the back of the green in an effort to transition it out so we can have the same consistent look as we do around the bunkers. |
|
Trenching out of the left bunker on #5. |
|
Soil being removed from the trench lines. All of this material throughout the project was moved by hand, shovel by shovel. |
|
Finishing the drain lines. |
|
Gravel being installed. |
|
The finished product waiting for sand and sod. |
No comments:
Post a Comment