Day #14, Bunker Renovation, 'Good Day Sunshine'

'Good Day Sunshine'  from the Beetles came to mind on Day #14 of our Bunker Renovation project.


#18 IS COMPLETE!!
#18 sod work was completed yesterday.  When I say complete means that the major part of the work is completed.  We might have some outflow trench lines to work on and other areas that need some minor work but for the most part it has been completed.  You can see from the picture that we have at least doubled the entry approach into the green.  The right side bunker was enlarged into the pot bunker and the right green side bunker was filled in.  the left bunker was filled in about 20 feet in the back and was brought forward slightly.

The staff dug out the right side of #4 in preparation for Kye to do his work.  The right front bunker of #7 was almost completed with some minor sod work to finish.  The right rear bunker was trenched and cleaned out in preparation for today's work.  We hope to get the left side bunker of #7 completed and all of the sod work done.  We tried to trench #6 but it is still too wet.  We have moved to #4.

Kye was working on #5 left side and moved to the right side in the P.M.  He will move to #4 right side this morning.  He will be on #8 on Thursday and it sounds like potential rain coming.  If rain stays away Friday he will move to #13.

#5 Left bunkers shaped.

Kye working on the right side of #5.

Staff removing spoils from #7 right front.

Installing drainage in the right front #7 bunker.

Adding sand in #7 right front.

Sodding the banks.

Additional sodding work.

Finished for the day.

Another view of the right front bunker #7.