Chances are we will receive some rain tonight. For our sake I hope not. A little soothing music to go through the blog this evening.
Sorry about the picture below. We completed our work toward sunset and light was depleted when I finally got around to getting the shot. I will get you a better picture tomorrow. The staff worked a great deal of the day on #7. They also cleaned out the drainage trenches from #4, sodded the banks of #4, place zoysia on the approach of #6 and cleaned out the bunkers of #8 before Kye began his work this morning. If we are able to work tomorrow, we expect to get the left side of holes 4 and 6 completed. If we are able to work Saturday, we will begin our work on #5. We will also have to clean out #13 on Friday in preparation for Kye's work on Saturday.
Kye completed some minor work on #4 and moved into #8. He has a little more work on #8 and will then move to #13 if we do not get too much rain overnight.
So, where are we in the project.
Bunkers completed (includes the 4 on #14). 15
Bunkers under construction. 9
Bunkers waiting to be renovated 13
Total Bunkers including the practice 37
#7 is COMPLETE! |
The staff laying the new fairway approach zoysia sod that covers part of the front bunker. |
Digging out the right bunker of #8. |
#8 left bunker complete. |
#8 right bunker near completion. |