Showing posts with label 2 tee renovation. Show all posts
Showing posts with label 2 tee renovation. Show all posts

Saturday, April 13, 2019

Sodding Zombies

Not much of a zombie guy but the staff has been getting that sod zombie strut going pretty good the last couple of weeks. They laid another 500 yards on holes 5 left rough to finish the bunker surround area. 7 back right bunker entrance, 2, 11, and 15 approach's and the east side of the practice green area were all sodded. Also a couple of stump holes were covered up and some repair on 4 approach. Pulled up some good bent grass on the approaches and laid it on damaged collars. Normally when we have cut off larger areas for repair, we've used a tractor with a blade and the backhoe as well as a dump truck but its been too soft and the areas are pretty sensitive for large equipment. All these areas were hand picked up. We were able to place the sod nearby this week after our backhoe repaired which kept them from having to load into carts and then unload onto the ground. Staff did a killer job on all of this work!


Left collar on #11 repaired.

Right collar repair 11.

15 stripped and waiting on sod.

Right side of 15 laying sod.

15 complete


We had completed part of the practice green area near the pro shop and looked at the Pearson Lane side and had to clean it  up as well. Aerified it heavily and then put a couple yards of compost in place to help soil structure a little.


Guys laying the sod on practice area.

Its been mentioned could we place some zoysia around so you can practice approach bump and runs so we did a decent sized strip on the east side of the practice green. Not really a place to be chunking out areas of sod but should be able to practice and few bump and runs. We might have to close sections of this during the season when play has worn it down a bit.
We also put some entrance and exit areas on the  pro shop side to try to spread the walk on and off area. We hope the soil modification, irrigation and aerating we will be doing will help keep this area looking good as well.

From the pro shop walk way. Did a larger cut out of zoysia neared Doc Ott's clock area.

Finished the area between the bunkers. Still have to repair the sod trench line from new irrigation.
Another look on 5.

2 approach repair and clean up.

2 approach

The mowing of greens are becoming more regular along with rolling. The first mowing of rough, tees, tee surrounds, fairways occurred this week and bunkers were trimmed up. Finishing up on our pre-emergent applications and we do have a great deal of broad leaf weed control that will take place over the next couple of weeks. Dandelions, clover and some cool season weed control.

We did some finish grading around the new 2 tee complex. Trying to get our laser leveling contractor in over the next week. We are going to have to dig out part of the back tee. The soil is soft and pumping so we will dig it out this morning and put some good hard Glen Echo clay in its place. Little video below showing the smoothed out area.

https://www.youtube.com/watch?v=_KPSyWUcEn0



Update on the repair to the back of the tee. Dug out a 10' x 12' section of the back of the tee this morning and back filled with some Glen Echo clay. The soil that was originally used was excessively wet and plastic like not allow the surface to firm and ultimately would have settled. The new soil should improve the situation.

Skip dug out  about 2' of fill that ended up being too plastic/rubbery.

Back filled, packed and smoothed over.

Friday, April 5, 2019

2 Tee Renovation and a Great Deal of Other Work to Discuss

March 22nd and 23rd we did the rough in of the new tees on #2. Due to the movement of a great deal of soil and wet conditions every 3-4 days, we are at a pause in work on this project.
I would hope if we can get dry in the next week or so we will get the surrounding area of the tee finished graded and prepared for sod. The teeing ground will be tilled and laser leveled by Schaefer-Meyer we hope within the next couple of weeks and then sodded so that the tee will be open for play by mid-May.
View from the front of the tee complex. Tees are now set up as 2 separate tee boxes.
From behind the tee complex. Sorry for the poor pictures, just looks like a pile of dirt from this level. Had my drone in the air the other day to take pics and crashed into a tree. Once I finish the repair, I will give you an overhead view.


Being the largest group of maintenance folks on staff at Glen Echo, our crew has been assisting in other areas. We spent about 20 man hours power washing the pool wall both inside and out. Also power washed all the walk ways in the front of the building and a part of Pearson Plaza. The staff power washed some of Limestone window sills that we did not get completed last season. The staff  with some able bodied assistance have also been busy inside the pool area removing some over grown shrubbery and pruning others. We we were in the process of mulching the upper wall bed when our loader broke down earlier in the week. Once it is back up, we will finish the mulching of this area. 

We will also be power washing the swimming area of the pool and installing new drain lids and plastering in new frames for the pool system. We will be managing most of the mechanical start up of the pool this season. I attained my pool operator certification for the pool over the winter.

The staff have also been involved in stringing the patio lights and moving equipment to the patio since warm weather is on its way.


Randy power washing the walk way in the front of the clubhouse


This week the staff have been extremely busy with sod work. Over 450 yards of old sod was removed and replaced with both fescue and zoysia. HATS OFF TO THE CREW THIS WEEK!! Our loader was broke down and we had to load the sod into carts and then unload it from the carts.  Normally we place the sod right in the area of work so double work for the guys this week because of the repairs taking place to our loader.

We first completed the tree removal stump repair and root removal on the old tree near 11 green. This was replaced with fescue.


Area to the right of 11 green. A large amount of roots had to be busted out by hand using axes and shovels.
                                                       The finished area off the front right of 11 green.


We then moved to #5 left bunker area. This area has a number of contributing factors to its look. Small area with a great deal of foot and equipment traffic. Last year we tried to resolve some of it with walk mowing the area. Significant shade and drought is the biggest reason for its decline. A large Pin Oak is growing right in the middle of this area and robs it of sunlight and much needed moisture. We stripped the old sod away, trenched in some new irrigation heads that will hit just in this area. We aerated it and put in a couple of yards of leaf compost. The area was then dragged with a metal drag to break of the dirt turds and move some of the compost into the holes. Sod was then added. Should see some improvement we hope with new sod and the other work we completed. We still have some additional areas to sod around the tree and bunker and will complete this hopefully next week.

Tree on the left is a beautiful specimen set back in the proper area on the hole. Tree on the right is being over shaded and basically is growing on one side. Leaves, acorns, and other material fall into the bunker regularly. The shade and moisture depletion is significant.
This is the trench that is about 15' deep and shows the network of tree roots from this tree.
Small 2-3" long turf roots have no chance in a competition for resources with these trees.
Aeration completed so that we can then add compost to improve the soil.
Compost added to the area.
After the area was dragged with a metal drag. Cores busted and some compost moved into holes.
Staff finishing up the sod work. You can still see the weakened turf around the tree. It will be replaced in a few days.

Complete

The staff worked on the 13th approach today and also did a smaller amount of work on the 18th approach. We removed the bent grass sod, repaired part of the collar on 13 and part of the collar on 16. They removed the rest of the material and then laid zoysia in its place. We also had some bermuda contamination and very weak turf in front of 18 approach which was pulled up and replaced.
 
                Bent grass sod being reused on collar on 13.

Finishing the removal. All of this work is being done by hand.
Zoysia sod being laid on 13 approach 
The finished area.
Jason Cutting the old material off of 18 approach.
The look from the left side bunker.
Same area but from below the area.
Finshed area looks great. Still some weakness in front which we will work on improving with aeration, compost and traffic control from our mowing units.