Today, we ripped off the asphalt covering to the bridge and cut a hole in the concrete spillway to check how much of gravel has been eroded from underneath the spillway. Our plan is to pour concrete under the spillway to reinforce the spillway and protect from future erosion. The upper part of the spillway needs some patching and the rusted bottoms of the galvanized spillway pipes will receive the same treatment we did last season to the spillway between the two small lake on #10. We will cut the rusted section of the pipe and place a new concrete flume bottom so the water will travel through the spillway and empty into the lower lake. Our last task will be to place a new concrete bridge surface for carts and walkers to cross the area.
In the meantime, please use caution when crossing the bridge by foot or by cart. This work should take a week or so depending upon rain and lake levels.