Thursday, August 12, 2010

Fairway aeration work

With our schedule disrupted from weather and mechanical issues, we continue to get our fairways aerated a few each week.  #2,3,4,5, and 16 were completed this week which leaves us with 7, 10, 11, and 12 to complete which we plan to finish on Monday.  What should have been a two-three day process has been pushed into nearly 4 weeks but the fairways are recovering nicely and will be in great shape for the fall.  The middle of August is the latest we want to aerate zoysia so it has enough time to recover before dormancy sets in by late October.

No comments: