Here's more if you have not had enough.
The staff got a good 6 hour day in on Saturday and finished the left bunker on #4 and most of the left bunker on #6 and the fairway approach. We still have a little more work on the back left of 4 and some sodding on #6. We did not receive any rain on Thursday night but did receive 8/10" of rain on Saturday night which worked out great for the project. A good thorough watering of the new sod and soil around the bunkers and we should be dry by Monday to begin again. The plan this week is to complete #5 and then the right side of #4. Maybe we will be able to start on #8 before the end of the weekend. We will be tearing out #3, #12 and probably #17 this week. Depending upon Kye's work, we might need to tear out #1 and the practice bunker. We also have #6 right side to tear out as well.
Kye almost finished #13 and has just some minor shaping to do on Monday. He will then move on to #3
and will be finished with it on Tuesday. He will then move to #12 which should be completed on Tuesday or early on Wednesday. He will then move to #17 which will take a day. Depending upon the weather, #1 and the practice could be finished on Friday/Saturday. We do also have to finish the right side of #6 which will be early next week.
Left bunker drainage install before sand was put in the bunker on Friday. |
The left bunker of #4 near completion on Friday afternoon. |
Almost completed Saturday morning except for some work on the top left corner at the sprinkler heads pictured above. |
The view of #6 with the new zoysia fairway approach. We have to complete some sodding and a little more clean up around the left bunker. |