The staff completed the renovation to the front of the white tee on 7 today. It was backfilled with soil, 3 drain lines were dug across it to reduce water pressure in the bank to hopefully stop the hillside from sloughing off again. Sod was laid on it today. 

To our young walkers, please stay off this area or you might end up injured from wet and soft conditions. Should be good to go in 2-3 weeks.


Skip using a mini-excavator to trench across the bank.



Laying the sod. Decided to use Bermuda grass due to its ability to deeper rooting and survive the summer heat.